Josh and I have been discussing plans for the upcoming release; below is what we've come up with so far. This is loosely based on past 0.4x plans. I'll follow up this email with explanations for the major differences. Meanwhile, feedback would be appreciated.
# Period Tasks Notes
- Open development.
- Chill. Development focuses on wrapping up Update tutorials and other docs
- Frost. Experimental Branch is forked B Post inkscape-0.91-pre0.tar.gz Release Notes should be >90% filled in.
- Feature Freeze. Stable Branch is forked from Mainline B String Freeze No further string changes allowed on Stable Branch. T Finalize tutorials to be shipped with release Finalize other docs included in the release Finalize about screen A Finalize Release Notes except Known Issues Translators work on translations. T
- Hard freeze. Only Release Wardens can commit to Stable Branch B Finalize codebase translations T
We've tried to ensure ample time for doing translations in this plan, by establishing String Freeze during Feature Freeze, and allowing until Hard Freeze for translation work to be done. Beyond code, this also attempts to get all translatable documentation finalized relatively early on.
Release Notes are also finalized a bit earlier, in order to permit time for anyone wishing to create translations of them. The only major thing I can foresee changing significantly are the Known Issues; I figure that's less critical to be translated though.
Finalize Known Issues section of Release Notes Finalize packaging scripts Post additional inkscape-0.91-pre*.tar.gz releases
Release. Post inkscape-0.91.tar.gz Post packages Post official announcements Plan 0.91.1+ release(s), if needed
Open development.