I've marked off the 0.92 items that were done from the Roadmap. A few things weren't finished and I've bumped them forward to 0.93. Some stuff I'm not certain of; if anyone else knows please update accordingly.
The 0.93 list of objectives looks more ambitious than I suspect the project can achieve within the coming year, and should be realigned to better forecast what's likely to be done.
A few items from the 0.93 roadmap are already under way:
* Gtk3 & drop Gtk2 * Git & drop bzr * CMake & drop autotools/btools/etc. * C++11 compiler hard requirement
I think we could safely add:
* OS X native packaging
What else could be considered to be added?
These I'm not so sure about, and might be candidates to postpone, if no one is looking at working on them presently:
* Flip y-cooridinate to match SVG * Dependency reorg * Unit test framework and major test case expansion * Windows uninstaller * New Swatch dialog
Thoughts on the above? Or any other Roadmap modifications that should be discussed?
Bryce